Items Sl No. Name of the Monument Year/Period Of Construction During Whose Reign Remarks
Roads 1 Seuni Ali(A.T.Road) 1650 Swargadeo Jaydhawaz Singha Jorhat to Gowrisagar48Km.Constructed by Boduli Borphukan.
2 Dhudor Ali 1681-1695 Swargadeo Godadhar Singha Kamargaon to Joypur touching Morioni Total length 211 Km.
3 Kharikatia 1696-1714 Swargadeo Rudra Singha Kharikatia to Titabor
4 Mohbondha Ali 1795-1810 Swargadeo Kamaleswar Singha Jorhat to Mohbondha
5 Kamarbandha 1795-1810 Swargadeo Kamaleswar Singha Jorhat to Kamarbandha
6 Malow gohain Ali 1751-1769 Swargadeo Kamaleswar Singha Desoi to Bosa
7 Susandebandha Ali 1795-1810 Swargadeo Kamaleswar Singha Within Jorhat
8 Choladhora Ali 1795-1810 -do- Within Jorhat
9 Borpatra Ali -do- -do- Within Jorhat running infront of J.B.College
10 Na-Ali 1796 -do- Jorhat to Titabor
Holly Temple 1 Hatigar 1812-Half done 1817-completed Swargadeo Chandrakanta Singha Constructed by Purnananda Buragohain. 5Km from Jorhat on the way to Sibsagar
2 Burigosani Than or Dewal 1794-1795 Garuinath Singha chandra Kt.Singha Shifted to bank of river Bhogdoi.Now on the side of Dewal Road.
3 Garakhiadol Temple(Shiva Temple) 1714 Swargadeo Siva Singha 7 Km from Jorhat.
4 Borbheti Than (Originally moneastery) 1769-80 Swargadeo Rajeswar Singha Constructed by Muwamoria Priest Ashtabhuz, 7Km from Jorhat town.
5 Dhekiakhowa Bornamghar 1497-1539 Swargadeo Suhung Myung By the devotees of Madhavdev.
Mone-astery 6 Dakhinpat Satra 1662 Swargadeo Jaidhwaj Singha
7 Garmur Satra -d0- Swargadeo Jaidhwaj Singha
8 Kamalabari Satra 1552-1603 Swargadeo Khoraroja At Majuli river island.
9 Bengenati Satra 1524 Swargadeo SuhungMyung -do-
Tanks 1 Rajmow Pukhuri 1816 Swargadeo Chandra Kt.Singha Near Jorhat Stadium
2 Hatigar Pukhuri 1812-Half done
1817-completed
Swargadeo Chandra Kt.Singha Construction started by Purnanda Buragohain but completed by Rushinath Buragohain
3 Katoki Pukhuri 1810-1818 -do- Within Jorhat town
4 Mitha Pukhuri 1810-1818 -do-
5 Bongal Pukhuri 1819-1820 Swargadeo Chandra Kt.Singha Dredged by Rupsing Subedar
6 Borgohain Pukhuri 1820 -do- Dredged by Borgohain
7 Choladhora Pukhuri 1820-21 -do- Dredged by Choladhora Phukan
8 Kuwari Pukhuri 1810-1818 Situated at Lichubari constructed by the queen of Garuinath Singha
9 Bolia Gohain Pukhuri -do- -do- At Lichubari Constructed by Dambaru Gohain alias Bolia Gohain
Burrial tombs 1 Rajamaidam i)1846 ii)1852 Raised during Brithsh period i)Maidum of Puranadar Singha
ii)Maidum of Swargadeo Kamaswar Singha
2 Lachit Maidam Singha 1672 Swargadeo Udayaditya Singha At Hoolungapara 16 Km from Jorhat.
3 Purnananda Buragohain Maidam 1817 Chandra Kt.Singha Washed away by Bhugdoi .It was near Macharhat.
Ram-parts 1 Ladoigar 1603-1641 Swargadeo Protap Singha 12 Kms to the east Jorhat.
2 Deberapara Gor 1552-1603 Swargadeo Khoraroja 30 Kms from Jorhat
3 Mohgor 1603-1641 Swargadeo Protap Singha To the North of Jorht touching Mohuamukh
4 Borgheta gor 1794-95 Swargadeo Gaurinath Singha From Bosha to Kaliani under Golaghat district..
others 1 Disoikuth(Army cantonment) 1789 -do- Purnanda Baruagohain
2 Hatigarh (Elephent trap) 1603-1641 Swargadeo Pratap Singha A pair of ramparts utilised as elephant traps.